PC Gold declares 951,000 oz Probable Ore Reserve at Spring Hill as PFS sets A$413M build cost
The Northern Territory gold study values the project at A$1.59bn pre-tax at A$5,500/oz; about 12% of planned ounces are Inferred and no funding is in place.


PC Gold Ltd (ASX: PC2) has declared a maiden Ore Reserve of 951,000 ounces for its Spring Hill gold project in the Pine Creek goldfield of the Northern Territory, about 200 km south-east of Darwin. The Reserve, released with a pre-feasibility study (PFS) on 24 November 2026, is 35.5 Mt at 0.83 g/t gold and is entirely in the Probable category.[1]
It is drawn from a July 2026 Mineral Resource of 75.9 Mt at 0.8 g/t gold for 1.92 Moz at a 0.3 g/t cut-off. Of that, 1.23 Moz is Indicated and 0.68 Moz Inferred. The company says 77% of the Indicated ounces converted to Reserve; Inferred material inside the mine designs was treated as waste.[1]
Readers comparing figures should note that the 1.92 Moz is the same estimate PC Gold first published in July as 1.51 Moz at a 0.5 g/t cut-off. The larger number reflects the lower cut-off used for the PFS, not new drilling.[1]
Resource and Reserve by category
| Estimate and category | Tonnes (Mt) | Grade (g/t Au) | Contained gold (koz) | Cut-off |
|---|---|---|---|---|
| Resource: Indicated | 47.3 | 0.8 | 1,234 | 0.3 g/t |
| Resource: Inferred | 28.6 | 0.7 | 681 | 0.3 g/t |
| Resource total (inclusive of Reserve) | 75.9 | 0.8 | 1,915 | 0.3 g/t |
| Reserve: Proved | nil | - | - | - |
| Reserve: Probable, open pit | 34.96 | 0.80 | 901 | 0.3 g/t |
| Reserve: Probable, underground | 0.50 | 3.14 | 50 | 1.5 g/t stope |
| Reserve total (Probable) | 35.45 | 0.83 | 951 | - |
Resources are reported inclusive of the Reserve and must not be added to it. Reserve evaluated at A$4,500/oz; open-pit designs based on an A$6,000/oz optimisation shell at revenue factor 0.72; ounces are contained metal before processing recovery. Competent Persons as named by the company: Daniel Donald (Entech, FAusIMM) for the Reserve; Brian Fitzpatrick (Cube Consulting, MAusIMM CP) for the Resource. Source: PC Gold ASX announcement, 24 November 2026, Tables 1 and 2.
On our calculation, about 36% of the Resource ounces are Inferred. PC Gold says the resource covers about 1.2 km of strike, remains open, and that roughly 40,000 m have been drilled since the April 2026 assay cut-off; an update is targeted for March 2027.[1]
Study outputs and the assumptions behind them
The study plans a staged open pit mined alongside a small underground operation, feeding a new 4 Mtpa gravity and carbon-in-leach plant on site. Because the gold price is set in Australian dollars and costs are estimated in Australian dollars, the company says no exchange-rate forecast is needed; it equates A$5,500/oz to about US$3,685/oz at US$0.67.[1]
| Measure | Production target case | Ore Reserve case | Assumptions and basis |
|---|---|---|---|
| Gold price | A$5,500/oz | A$4,500/oz | Flat, real; about US$3,685/oz at US$0.67 (base) |
| Pre-tax NPV / IRR | A$1,591M / 66% | A$739M / 39% | 5% real discount rate |
| Post-tax NPV / IRR | A$1,239M / 56% | Not stated | 3.5% real; 30% tax; A$19.8M tax losses applied |
| Pre-production capital | A$413M | - | Plant to AACE Class 4 (-20% to +25%); incl. A$30.2M contingency |
| AISC (life of mine) | A$2,870/oz | - | Excludes closure (A$46/oz); royalties 6.7% of revenue |
| Gold recovered | 1,028 koz over 9.5 years | 9.4-year life | 94.1% recovery; ~120 koz a year CY2029-33 |
| Payback (pre-tax) | 1.3 years from first gold | - | First gold assumed January 2029 |
| Inferred share of target | About 12% of ounces (7.1% of tonnes) | Nil | About 65% of underground inventory is Inferred |
NPV and IRR exclude about A$17.9M of pre-FID spending. The first five years carry a higher head grade (~0.95 g/t) than the life-of-mine average (0.89 g/t) and the company says they are not representative of the whole mine life. Source: PC Gold ASX announcement, 24 November 2026, Tables 3 and 13, footnotes 1-6, Section 4.9.
Two parts of the economics deserve weight. The pre-tax valuation uses a 5% real discount rate; on the company's own test, an 8% rate cuts pre-tax NPV to A$1,317M. And the Reserve-only case, which excludes all Inferred material and uses a lower gold price, is worth less than half the headline.[1]
How the value moves with the gold price
Data table
| Item | A$M, pre-tax NPV at 5% real |
|---|---|
| A$4,500 | 865.0 |
| A$5,000 | 1,228.0 |
| A$5,500 (PFS) | 1,591.0 |
| A$6,000 | 1,955.0 |
| A$6,500 | 2,318.0 |
| A$7,000 | 2,681.0 |
The A$4,500/oz point is the production-target plan at that price, not the Ore Reserve case (A$739M). Source: PC Gold ASX announcement, 24 November 2026, Table 16.
The company says the project is most sensitive to gold price and head grade: a 10% adverse move in either takes pre-tax NPV from A$1,591M to A$1,192M. A 10% rise in capital cost reduces it to A$1,538M.[1]
Funding need and approvals
PC Gold had about A$85.5M in cash at 30 September 2026, which it says funds the definitive feasibility study (DFS), drilling and pre-decision works. The A$413M build would have to be raised after that.[1]
On our calculation, that capital need is about 1.3 times the market value of roughly A$310M the company cited on 24 November. PC Gold says it will assess bank project finance, equity and other sources during the DFS, and warns that funding terms may dilute shareholders.[1]
Approvals set the pace. Commonwealth and Northern Territory approvals cover only a Stage 1 open pit; the full plant, tailings dam and mine need new referrals, planned for Q1 2027. The company rates disturbance to the Ghost Bat, listed as Vulnerable under the EPBC Act and roosting in old workings, as the project's highest risk.[1]
“Importantly, the maiden Ore Reserve of 951,000 ounces has been estimated at a conservative A$4,500 per ounce and is built on a Resource that covers only 1.2 kilometres of strike.”
Next gate: DFS and investment decision
The company plans 20,000 m of underground drilling from Q1 2027 aimed at converting the high-grade Link Zone, a resource update in March 2027, then a DFS, updated Reserve and final investment decision in Q3 2027. Mining would start in Q3 2028 with first gold in Q1 2029, timing the company calls indicative.[1]
“We are funded through the DFS to a Final Investment Decision targeted for the third quarter of 2027, and our focus is now firmly on moving Spring Hill towards first gold in early 2029.”
Questions readers ask
- Why does PC Gold quote two different NPVs?
- The A$1,591M figure is the pre-tax value at a 5% real discount rate; A$1,239M is after tax at 3.5% real. Both use A$5,500/oz gold and include Inferred material.[1]
- Does Spring Hill already have approval to mine?
- Only for a Stage 1 open pit. The expanded mine, plant and tailings facility in the PFS need new Northern Territory and Commonwealth approvals.[1]