Norwest Minerals' Bulgera scoping study: a A$54m heap leach worth A$89m at A$5,800 gold, on its own numbers

The study plans 87,000 oz over 57 months. By our arithmetic the project's pre-tax cash flow falls to zero near A$4,440/oz, and 22% of the feed is Inferred.

Piles of low-grade gold ore under cyanide heap leaching in the Cripple Creek district, Colorado
Photo: James St. John via Flickr, CC BY 2.0 (cropped)
Bar chart of Bulgera pre-tax cash flow by gold price: A$5,000/oz 47 million; A$5,500 89 million; A$5,800 base case 114 million; A$6,000 131 million; A$6,500 172 million.
MinStrata graphic; data: Norwest Minerals ASX announcement, 23 Nov 2026, Table 9

Norwest Minerals (ASX: NWM) says a standalone open-pit and heap leach operation at its Bulgera Gold Project in Western Australia could earn a pre-tax net present value of about A$89 million at a gold price of A$5,800 an ounce. It released the scoping study to the ASX on 23 November 2026.[1]

A scoping study is the earliest formal stage of mine evaluation. Norwest's own cautionary statement says the study rests on low-level technical and economic assessments that cannot support Ore Reserves, and that it gives no assurance of an economic development.[1]

The headline numbers and the assumptions behind them

Bulgera scoping study: company figures at the A$5,800/oz base case · A$ million, real September 2026 dollars, pre-tax, ex-GST, unless stated[1]
Bulgera scoping study: company figures at the A$5,800/oz base case (A$ million, real September 2026 dollars, pre-tax, ex-GST, unless stated)
MeasureCompany figure
Mineralised material mined6.36 Mt at 0.57 g/t Au (diluted)
Waste mined / strip ratio19.8 Mt / 3.1:1
Gold recovered87,000 oz (117,000 oz processed)
Mine life57 months
Net revenue483
Life-of-mine capital60 (54 pre-production, incl. 3 contingency)
Operating cost incl. closure309
Pre-tax cash flow114
NPV at 7% / IRR89 / 76%
PaybackAbout 24 months

Scoping study accuracy is stated as plus or minus 35%. NPV and IRR are pre-tax; the company has not modelled tax. Source: Norwest Minerals ASX announcement, 23 November 2026, Tables 1, 7 and 9.

Three assumptions carry most of that result. The first is price: a flat A$5,800/oz, which Norwest says is within 3% of the 30-day trailing average spot price. The pits were designed on A$5,400/oz shells, and the resource was constrained at A$5,000/oz.[1]

The second is recovery. Heap leaching stacks crushed ore on lined pads and trickles a cyanide solution through it, which is cheaper than milling but usually recovers less gold. Norwest assumes a weighted field recovery of 74% to 75% at a 25 mm crush.[1]

The third is the omission of tax. All values are pre-tax because, the company says, ownership, financing, capital allowances and the use of its carried-forward tax losses are still to be decided.[1]

How much margin the gold price leaves

Bulgera gold price sensitivity, as reported by Norwest · A$ million pre-tax; IRR in %[1]
Bulgera gold price sensitivity, as reported by Norwest (A$ million pre-tax; IRR in %)
Gold price (A$/oz)Pre-tax cash flowNPV 7%IRR
5,000473232%
5,500896859%
5,800 (base)1148976%
6,00013110388%
6,500172139118%

Costs and physicals held constant across prices. Source: Norwest Minerals ASX announcement, 23 November 2026, Table 9.

Norwest says each A$100/oz change in the gold price moves undiscounted pre-tax cash flow by A$8.4 million. Extending that line downward from the A$5,000 case, cash flow would reach zero at about A$4,440/oz. That is our calculation, and it assumes costs and the mine plan stay fixed, which a real operation would adjust.[1]

Another way to see the margin is cost per ounce. Dividing the A$309 million operating cost by 87,000 recovered ounces gives about A$3,550/oz; adding the A$60 million of capital takes it to about A$4,240/oz. Both figures are our arithmetic, before tax and corporate costs, and are not a company AISC figure.[1]

What sits under the production target

The study draws on the 1 July 2026 Mineral Resource for mining lease M52/1085: 8.7 Mt at 0.68 g/t for 191,000 oz, at a 0.24 g/t cut-off. Of that, 6.6 Mt at 0.68 g/t for 145,000 oz is Indicated and 2.1 Mt at 0.68 g/t for 46,000 oz is Inferred.[1]

The mine plan uses only the highly and moderately weathered oxide material, which leaches readily, and leaves out 1.9 Mt of fresh rock at 0.84 g/t for 51,000 oz. Norwest says 78% of processed material is Indicated over the mine life and 84% in the first 12 quarters.[1]

  • The Inferred share (about 22%) may never be upgraded; the company states there is no certainty further work will convert it.
  • The A$54 million of pre-production capital is not funded. Norwest says funding may be dilutive, or it may sell or joint-venture part of the project.
  • The Price pit extends beneath Bulgera Creek, and the creek crossing and diversion need heritage and waterway approvals that depend on surveys still to be done.

“We are now advancing into Pre-Feasibility Study workstreams to unlock further upside, including fine-crush recovery optimisation, infill drilling of Inferred material”

Charles Schaus, Chief Executive Officer and Director, Norwest Minerals[1]

Reporting basis

The study was compiled by Norwest with Orelogy (mine planning and financial model), ALS Metallurgy and Kappes, Cassiday & Associates Australia (metallurgy), NewPro (process plant and costs) and MBS Environmental. The Competent Persons named are Andrew Hollis of Orelogy (MAusIMM) for mining, scheduling and the financial model, Paul Newling of NewPro (FAusIMM) for processing and costs, and Randall Pyper of KCAA (FAusIMM) for metallurgy.[1]

The Mineral Resource was compiled by Stephen Hyland (FAusIMM) of Hyland Geological and Mining Consultants under the JORC Code (2012), as reported on 1 July 2026.[1]

What comes next

Subject to funding, Norwest plans a pre-feasibility study from January to December 2027. It will test a finer crush for higher recovery, infill-drill the Inferred material, look at deeper fresh rock and sample historic oxide waste dumps as possible low-grade feed.[1]

Questions readers ask

Is the A$89 million NPV what the project is worth?
No. It is a pre-tax, scoping-level estimate at plus or minus 35% accuracy, at a flat A$5,800/oz, and 22% of the feed is Inferred. It is not a valuation of the company.[1]
Does Bulgera have an Ore Reserve?
No. Norwest says the scoping study cannot support Ore Reserves and that further studies are needed first.[1]