Saturn Metals moves Apollo Hill investment decision to early 2028 after EPA sets public review

WA's environmental regulator will put the Leonora gold project to a four-week public review; the feasibility study also slips to early 2027.

The Mount Charlotte mine area at Kalgoorlie in Western Australia’s Eastern Goldfields
Photo: aussiejeff via Flickr, CC BY-SA 2.0 (cropped)
Timeline for Saturn Metals' Apollo Hill gold project. 21 July 2026: mining lease M31/496 granted. 23 September 2026: environmental review document submitted to the WA EPA. 13 to 19 October 2026: EPA seven-day public comment on the referral. 24 November 2026: Saturn says the EPA advised a four-week public review. Early 2027: definitive feasibility study targeted. Early 2028: final investment decision targeted, previously late 2027.
MinStrata graphic; data: Saturn Metals announcements 21 Jul, 28 Oct and 24 Nov 2026; WA EPA Consultation Hub

Saturn Metals Limited (ASX: STN) has pushed back the planned investment decision on its Apollo Hill gold project near Leonora, Western Australia, after the state's Environmental Protection Authority asked for its application to be opened to public review. The company disclosed the change in an announcement on 24 November 2026.[1]

Saturn said the EPA advised that the application will be subject to four weeks of public review, followed by a period of assessment by the authority. Together, it estimates, the two steps could add about three months to the development timeline.[1]

That moves the planned final investment decision (FID) from late 2027 into early 2028. Apollo Hill is a pre-development project: Saturn has a pre-feasibility study, a maiden Ore Reserve and a granted mining lease, but has not made a construction decision.[1][5]

What the EPA has on record

The EPA's consultation site lists the Apollo Hill Gold Project under its seven-day comment on referrals, open from 13 October and closed on 19 October 2026. That stage asks the public whether the EPA should assess a proposal and at what level.[2]

The referral describes open-pit mining, dewatering, waste rock landforms, ore stockpiles and on-site processing, about 170 km north of Kalgoorlie and 50 km south-east of Leonora. It covers clearing of up to 3,534 hectares of native vegetation and taking up to 6.3 GL of groundwater a year.[2]

Saturn's September quarter report said it submitted a Section 38 environmental review document to the EPA on 23 September 2026. The company's 24 November statement does not name the level of assessment the EPA set, and MinStrata could not retrieve the EPA's published decision; the EPA website refused automated access.[3][1]

Apollo Hill development milestones: before and after the EPA advice · Calendar timing as stated by the company[1][3]
Apollo Hill development milestones: before and after the EPA advice (Calendar timing as stated by the company)
MilestoneEarlier company timingTiming stated 24 Nov 2026
EPA processSubmission 23 Sep 2026; no public review mentionedFour-week public review, then EPA assessment
Definitive feasibility studyDecember 2026 ('next month')Early 2027
Final investment decisionLate 2027Early 2028
Start of plant constructionEarly 2028, subject to FID (Oct 2026 quarterly)Not restated; construction shown from 2028
First goldNot stated in these documentsTargeted early 2029 (company timeline chart)

The company's timeline is marked indicative and subject to permitting, approvals, funding and an investment decision. Sources: Saturn Metals announcements of 24 November 2026 (Figure 1) and 28 October 2026 (September quarter report).

The study delay

Saturn also delayed its definitive feasibility study (DFS). It said financial model reviews, benchmarking and independent engineering peer reviews found ways to further optimise the project, and it chose to fold them into the study.[1]

Managing Director Ian Bamborough linked the two changes, saying in the announcement that the longer timeline gives room to improve the study.[1]

“I believe that by utilising the relatively short and incidental extension to the Project timeline to optimise the DFS, we will enhance the Project with more comprehensive engineering and better integration into Saturn's emerging Project execution plan”

Ian Bamborough, Managing Director, Saturn Metals Limited[1]

The company did not quantify any change to costs or project economics. It said it is confident that supplementary information the EPA may request has already been commissioned or completed, while warning more requests could arise.[1]

What is being permitted

Apollo Hill is planned as a large open pit with heap leach processing. Its June 2026 Mineral Resource is 174 Mt at 0.51 g/t gold for 2.83 Moz above a 0.20 g/t cut-off, inside a pit shell run at A$5,000/oz.[4]

Apollo Hill Mineral Resource (June 2026) and Ore Reserve (December 2025) by category · Mt; g/t Au; contained koz[4][5]
Apollo Hill Mineral Resource (June 2026) and Ore Reserve (December 2025) by category (Mt; g/t Au; contained koz)
Estimate and categoryTonnes (Mt)Grade (g/t Au)Contained gold (koz)
Resource: Measured4.90.5587
Resource: Indicated1290.512,100
Resource: Inferred40.30.50643
Resource total1740.512,830
Ore Reserve (December 2025 PFS)104.60.471,586

The Resource total is the company's reported total, not our sum; figures may not add due to rounding. The Ore Reserve predates the June 2026 Resource and was reported with the 17 December 2025 pre-feasibility study; it is being updated in the DFS. Sources: Saturn Metals announcements of 3 June 2026 (Table 1) and 21 July 2026 (footnote 2).

The current Reserve and the 1.77 Moz pre-feasibility production target date from December 2025. Both are due to be updated in the DFS, which will rest on the larger 2026 resource.[5][4]

Funding position

Saturn reported cash of A$110.7M at 30 September 2026, after a A$100M placement and an oversubscribed A$21.28M share purchase plan. A further A$39.79M of placement funds from cornerstone investor Golden Crane awaited Foreign Investment Review Board approval at that date.[3]

The company said those funds are for front-end engineering, long-lead items, approvals and site establishment. Construction funding would be needed after the investment decision.[3]

Next milestones

The next public steps are the EPA's four-week review window and the DFS in early 2027, which Saturn says will carry an updated Ore Reserve. The company said it will update the market on permitting as appropriate.[1]

Questions readers ask

Does a public review mean the EPA has rejected Apollo Hill?
No. Saturn says the EPA advised a four-week public review of its application, followed by assessment. No decision on the proposal has been announced.[1]
Has the first gold target moved?
Saturn's updated timeline chart targets first gold in early 2029. Its earlier documents reviewed for this article do not state a first-gold date to compare against.[1][3]