Core Lithium (ASX: CXO) loads its first Finniss cargo since the restart: 10,000 t of spodumene at Darwin
The cargo grades about 5.1% lithium oxide and is sold through Glencore. Core expects a provisional payment in mid-December; the price is not disclosed.

Core Lithium (ASX: CXO) has started loading the first cargo of spodumene concentrate produced at its Finniss Lithium Operation in the Northern Territory since the operation restarted this year. The company told the ASX on 25 November 2026 that loading was beginning that day at Darwin Port.[1]
Spodumene concentrate is the processed lithium mineral that converters turn into lithium chemicals for batteries. Finniss lies on the Cox Peninsula, 88 km by sealed road from the port.[1]
The cargo and how it is paid
| Item | Detail |
|---|---|
| Size | About 10,000 wet metric tonnes |
| Grade | About 5.1% Li2O |
| Buyer | A major international lithium chemicals producer (not named) |
| Marketing | Glencore International AG, five-year agreement |
| Payment | Provisional payment mid-December 2026; final settlement after price, weight and assay |
| Source ore | Grants open pit |
Final proceeds are subject to adjustments for grade, transport costs and other commercial terms. Source: Core Lithium ASX announcement, 25 November 2026.
The announcement does not give a price or an expected cargo value, so the size of the December payment cannot be worked out from it. Core says final proceeds will be adjusted for product grade, transport costs and other customary terms.[1]
Where the restart stands
Core commissioned its upgraded dense media separation (DMS) plant and produced first concentrate in September 2026, within six months of the Finniss restart. It says optimisation is continuing and performance is tracking in line with expectations.[1]
Grants is a short-life source of early cash. The company expects mining there to continue to early in the fourth quarter of its 2027 financial year and to produce about 134,000 t of SC5-equivalent concentrate in total, while it develops the BP33 deposit. The production target was set out in Core's March 2026 restart announcement.[1]
“Cash flow from Grants will support the business as we continue developing BP33.”
The restart comes as another WA producer, Develop Global, said on the same day it would pause its Pioneer Dome lithium mine because of low prices, which shows how thin margins remain for higher-cost supply.[2]
Questions readers ask
- How much will Core be paid for the cargo?
- The announcement does not say. Core will receive a provisional payment in mid-December, with final settlement after the price, weight and assay are determined.[1]
- How long will Grants produce?
- Core expects mining at Grants to continue to early in the fourth quarter of fiscal 2027, producing about 134,000 t of SC5-equivalent concentrate in total.[1]